Tag: Tunnel Breakthrough

Upper Myagdi-1 Achieves Major Tunnel Breakthrough Milestone

MYAGDI, Sept. 10: The 35.5 MW Upper Myagdi-1 Hydropower Project has achieved a tunnel breakthrough from the adit to the dam section. The project, promoted...

Army Vows No Halt to Search for Those Trapped in Hydropower...

Kathmandu: The Nepal Army has said that search and rescue operations inside tunnels of flood-damaged hydropower projects will continue until breakthrough access is achieved...

Middle Kaligandaki Hydropower Project Achieves Key Adit-01 Breakthrough

Kathmandu: The breakthrough of Adit-1 tunnel has been achieved at the 66.3 MW Middle Kaligandaki Hydropower Project, which is under construction in Annapurna Rural...

Tanahun Hydropower Project Makes Major Breakthrough: Main Tunnel Complete, Project on...

Tanahun, 31,March2024 . The main tunnel of the Tanahun Hydropower Project, a 140 MW reservoir-based project under construction on the Seti River bordering Rishing...

Thulo Khola Hydropower Project to Start Generating Electricity Within 8 Months

KATHMANDU, Dec 10: The 21.3 MW Thulo Khola Hydropower Project completed construction of its tunnel on Saturday. According to the project, the 2,700 meter long tunnel...

Tanahun hydro’s Tunnel Breakthrough

June 6, 2021 , Tunnel Breakthrough of Approach Tunnel to Dam of 140- MW Tanahun Hydropower Project. The hydropower project is being built in Jhaputar of...

कालंगाको साढे तीन किमी सुरुङ निर्माण सम्पन्‍न

आश्विन १०, २०७७ बझाङ — निजी क्षेत्रको लगानीमा निर्माण भइरहेको सुदूर पश्चिमकै ठुलो कालंगा गाड जलविद्यूत आयोजनाको करिब साढे तीन किलोमिटर सुरुङ निर्माणको काम सम्पन्न...

MOST POPULAR