Tamakoshi V Hits 30% Progress, Tunnelling Under Way From Six Fronts

37

Dolakha — Physical progress on the domestically funded Tamakoshi V Hydropower Project has reached 30 percent. The project, where work had been halted for 10 months, has sped up construction after obtaining usage rights to land in a national forest area.

The project says it has dug three adit tunnels and is now excavating the main tunnel from six locations. Of the 8,850-metre main tunnel of the 99.8-megawatt Tamakoshi V, which is being built as a cascade project of Upper Tamakoshi, 2,635 metres have been excavated so far.

Ram Prasad Yadav, Managing Director of the Tamakoshi V company, said the Chinese company Sinohydro, which holds the civil works contract, is excavating up to 14 metres of the main tunnel per day from the six locations. Although the target is up to 20 metres per day, a shortage of explosives has had a minor impact on the project. Construction had earlier been obstructed because the forest-area usage rights had not been granted.

Tamakoshi V, being built under the Engineering, Procurement and Construction (EPC) model, was targeted for completion in June–July 2028. However, long government delays in granting usage rights to state forest land will push the project back somewhat.

For a year and a half after Sinohydro was awarded the civil works contract, work had been obstructed because of the forest-area usage rights at the construction site. Yadav said that now that the project’s legal complications are resolved, Sinohydro has accelerated work with a target of finishing in 15 to 18 months. “There are no legal complications from anywhere for building the project, and there will be no obstructions now,” he said. “Work has now gained momentum. If we don’t have to concrete the main tunnel, we will finish on schedule.”

Yadav said it appears the main tunnel will not need concreting. However, since the agreement with the contractor includes concreting the tunnel, discussions are under way to revise it. “Because the main tunnel is in extremely hard rock, it appears concreting won’t be needed, but the agreement requires it,” he said. “We are asking Sino to reduce the amount by not doing the concreting, and discussions are ongoing.”

He said the talks have not been positive because Sino insists it should receive the full contracted amount even if it does not do the concreting. If concreting is required, the project will only begin generation from March–April 2030, he said. Excavation for the underground transformer cavern has been completed. Similarly, work on the spillway tunnel, the ventilation tunnel and the access tunnel to the underground powerhouse has been completed, and 77 percent of the work at the underground powerhouse site is done, Yadav said. Construction is running 24 hours a day, he added.

Yadav said the electro-mechanical contract under Lot 2 has also been awarded, to the Chinese company Hongzhou. The company has already set up a camp at the project site to begin work and is carrying out design work. The project is estimated to cost Rs 21.14 billion.

The project’s financing modality is 30 percent equity and 70 percent debt. Of this, a memorandum of understanding has been signed for the Employees Provident Fund to provide Rs 13 billion in loans. Likewise, the Upper Tamakoshi project has proposed investing 10 percent. The project will be built with share investment from the general public and residents of the district.

The project will use the existing structures of the Upper Tamakoshi project, as Tamakoshi V is its cascade project. Its main works are the tunnel and the underground powerhouse. Because it will use the tailrace water of Upper Tamakoshi, there is no need to build a dam, a settling basin (desander) or headworks. Water from the tailrace will flow directly into Tamakoshi V’s tunnel. Since Upper Tamakoshi is a semi-reservoir (peaking) project and its pondage will be used, Tamakoshi V will also be considered a semi-reservoir project.

 