Kathmandu: Power supply will be cut for four days in Old Baneshwor and various surrounding areas of Kathmandu to strengthen the electricity distribution system and build an underground distribution network. The Baneshwor Distribution Center of the Nepal Electricity Authority (NEA) is cutting power to carry out work at various locations, including structure installation, raising high-tension (HT) cables, busbar installation and cable charging.
According to the notice issued by the distribution center, power supply will be cut in phases at different locations from Saturday, November 28 to Tuesday, December 1. The published schedule shows outages each day from 10 a.m. to 3 p.m.
The Authority is undergrounding the distribution system through the Kathmandu Valley Central and North Distribution System Strengthening Project. The notice states that power is being cut because, in areas where underground work under the project has been completed, structure fitting, HT and LT cable rising, cable charging and busbar connection still need to be done.
Outages in different areas over four days
According to the Authority, on Saturday, November 28, structure fitting and HT cable rising will be carried out at various locations in the KMC and Old Airport areas. That day, power will be off in Aagamannagar Marg, Alok Madhya Marg, Alok Tara Marg, Sabitri Marg and the Nirmala Bihar area.
On Sunday, November 29, busbar installation and HT cable charging will be carried out in the Old Airport area. The Authority says power will be off in Shankhamul Marg, the Everest Hospital area, the Mukti Tower area and around the Three Brothers petrol pump.
Similarly, on Monday, November 30, HT cable rising and busbar installation will be carried out in the Shankhamul and Dhobikhola areas. Power is scheduled to be off that day in the Alpha Beta, Buddhanagar and Bijuli Bazaar areas.
On Tuesday, December 1, structure fitting and HT cable rising will be carried out in the KMC area. That day, power will be off around the Ward No. 39 office and the Tinkune vegetable market.
Undergrounding work speeds up
To make electricity distribution in the Kathmandu Valley more organized, safe and reliable, the Authority is moving ahead with building an underground distribution system and strengthening existing infrastructure. Connecting the new underground system to the existing distribution network requires various technical work.
Structure fitting, high-voltage cable rising, busbar installation and cable charging are technical processes required to operate the distribution system. Because such work must be done with power shut off in the affected areas for safety reasons, outages are being scheduled for set periods.
The Authority said that if work is completed ahead of schedule, power may be restored earlier accordingly. The distribution center has also apologized for the inconvenience caused to customers by the outages.
Once the underground distribution system and network strengthening work is complete, it is expected to help make electricity distribution in the affected areas more organized.