Dhalkebar-Inaruwa 400 kV Transmission Line Commences Operation, Enhancing Nepal-India Electricity Trade

Kathmandu, 26 June 2024. The Dhalkebar-Inaruwa section of the Hetauda-Dhalkebar-Inaruwa 400 kV transmission line, currently under construction, has been put into operation. This project...

Nepal’s Third Largest 400 KV Hetauda Substation Complete, Ready to Transmit...

Kathmandu, 8 June 2024. Construction of 400 KV Hetauda substation has been completed in Hetauda sub-metropolitan city of Makwanpur-11 Thanabhayang for the strengthening and...

Minister Urges Expedited Completion of Crucial Hetauda-Dhalkebar-Inaruwa Transmission Line

KATHMANDU, Nov 21: Minister for Energy, Water Resources and Irrigation, Shakti Bahadur Basnet has expressed concern about the progress being made in the construction...

Hetauda-Dhalkebar-Inaruwa Transmission Line Construction in Full Swing, Despite Obstructions

Kathmandu, 27 October 2023. The wire-pulling work of the Hetauda-Dhalkebar-Inaruwa 400 KV double circuit transmission line project under construction for the strengthening of the...

Frequent power cuts become common across the country

Abrupt power cuts have been common occurrence across the country of late. this has left many to suspects if Nepal Electricity Authority has imposed...