Construction of substation in full swing to improve power supply in Kathmandu Valley, aims to be completed within a year

1615

Kathmandu, 5 Jan 2078. Nepal Electricity Authority (NEA) has taken initiative to complete the projects under construction as soon as possible for the improvement of power transmission and distribution system in Kathmandu Valley.

NEA has moved ahead with the aim of completing the projects under construction within a year to meet the growing demand of electricity in the Kathmandu Valley and to make the supply reliable and quality.

Projects such as construction of new substations, automation of existing substations, undergrounding of electric wires, addition and strengthening of new feeders and transformers are underway to make the power supply of Kathmandu Valley reliable, quality and modern.

NEA has started construction of transmission and distribution system infrastructure in the Kathmandu Valley with short-term, medium-term and long-term plans to consume 2,000 MW of electricity. The Government of Nepal, NEA’s investment, concessional loans from the Asian Development Bank (ADB) and Japan International Cooperation Agency (JICA) have put forward a comprehensive plan to improve the transmission and distribution system.

NEA Managing Director Kulman Ghising monitored the projects under construction on the spot and got information about the construction progress, ongoing problems and the work to be completed within a year.

Managing Director Ghising has requested to expedite the construction of 220 ÷ 132 ÷ 33 KV substation under construction in Matatirtha of Kathmandu, Futung, Teku, Chobhar, Thimi of Bhaktapur and 132 ÷ 33 ÷ 11 KV substation under construction in Changunarayan.

Ghising urged the project management, construction contractors and consultants to complete the construction of the project before the onset of winter next year. “If the substations under construction are not completed and brought into operation before next winter, load shedding may occur due to lack of infrastructure to meet the demand for electricity, so let’s complete the construction of such sensitive projects seriously,” he said.

The work has been hampered by the Department of Roads refusing to allow underground electrical wiring on the main road, obstruction by locals demanding route change, and in some places locals not allowing transformers to be placed near their homes. We are coordinating. ‘

A substation of 220 ÷ 132 ÷ 33 KV and 320 MVA capacity is under construction at Matatirtha to bring electricity from the Marsyangdi and Trishuli river reservoir areas to the Kathmandu Valley for distribution. Matatirtha substation, which is targeted to be completed by next September, is becoming a big hub for power supply in Kathmandu Valley.

Preliminary work has been started to supply five 11 KV feeders underground to the main road to supply electricity to Thankot, Satungal, Gurjudhara and other areas from the substation. After the operation of the feeder, the power supply of the area will be reliable and of good quality and the load work of Suchatar and Teku substations will be done.

Construction of 132-11 KV substation at Chobhar in Kathmandu has been started after obstruction in construction of Khokna, Bummati, Harisiddhi and Lamatar areas of Lalitpur under Thankot-Chapagaun-Bhaktapur 132 KV transmission line, which is considered important to improve power supply in Kathmandu Valley. The substation will have two power transformers with a capacity of 45 MVA.

The process of acquiring 12 ropanis of land required for construction of substation on the land of Himal Cement near Sukhabandargaha is moving ahead. A 132 KV transmission line has been constructed from Matatirtha to Chobhar.

If the Thankot-Chapagaun-Bhaktapur line had been completed, a ring of 132 kV transmission line would have been constructed in Kathmandu, Lalitpur and Bhaktapur. This would have increased the reliability of power supply and improved the quality of voltage We have made a plan to take it to Lagankhel substation in Lalitpur, ‘said Executive Director Ghising. “It has been designed. We are strengthening the existing Lagankhel substation to 132 KV. Then in the coming days we will take the line from there to Chapagaun and Harisiddhi underground.” This line is already ‘overloaded’.

NEA is constructing new substations of 132 ÷ 11 kV and 132 ÷ 11 kV in Futung by strengthening the 66 ÷ 11 kV substation in Kathmandu. Two substations of 45 ÷ 45 MVA capacity will be installed in both the substations. Electricity will be supplied to the area by tapping the Balaju-Chapali 132 KV double circuit transmission line at Futung substation.

The main civil structures of Futung substation are being constructed and the equipment has already arrived. After the operation of the substation, the power supply of Balaju area will be improved and the load of Balaju substation will be reduced.

Similarly, 132 ÷ 11 kV substation is under construction in Changunarayan of Bhaktapur while construction of Lapsiphedi 220 ÷ 132 ÷ 11 kV substation has not started due to local obstruction. The Lapsiphedi substation is being constructed in the Kathmandu Valley to distribute the electricity of the hydropower projects constructed in the Tamakoshi and Sunkoshi river reservoir areas. The substation will have 160 and 22.5 MVA capacity power transformers. A 400 kV double circuit Tamakoshi-Kathmandu transmission line is under construction from New Khimti substation in Ramechhap to Lapsiphedi.

Locals are obstructing the construction of 10 km transmission line from Lapsiphedi to Changunarayan substation, said Tara Pradhan, head of NEA’s project management directorate. The Chapali-Bhaktapur 132 kV transmission line will be tapped and taken to Changunarayan substation. The construction of the substation is targeted to be completed by next year.