Tanahun Hydropower Project Transmission Line Faces Policy Hurdles

276

Damauli (Tanahun) The construction of the transmission line for the under-construction 140 megawatts hydropower project has been delayed due to policy problems.

The construction under package 3 of the project has been delayed due to problems with the Ministry of Forests and Environment. Construction of the transmission line started in the Nepali month of Asoj in 2077 BS.

Indian KEC International Limited has the contract to construct the project. So far, 69 per cent work of the project has been completed, said Rajbhai Shilpakar, head of the Tanahun hydropower project. “Some problems relating to the Ministry of Forest have remained to be resolved. We have written to the Ministry of Forest through the Ministry of Energy for the resolution of the problems,” he said.

According to him, laying the foundations for 69 towers has been completed. Similarly, the construction of 33 towers has been over, and laying the foundations for 12 towers has been completed. Hoisting electrical cables has reached 0.9883 km. According to him, laying the foundation for the project is ongoing at a place. “The construction of the transmission line has sped up under package three along with packages one and two,” he said.

Under package three, KEC International Limited is constructing the 220 kV 36 km double circuits transmission line spanning from Damauli to Bharatpur of Chitwan. The contract deadline was extended until 19 December 2024 after there was a delay in the completion of the project due to COVID-19 and the inability to acquire permission from the Ministry of Forest to cut down trees within the project site. The project aimed to be completed by May 2022. A total of 23 ropanis and five aanas of land will be acquired for the project.

The land within Byas Municipality-13, Bandipur Rural Municipality-6, Aabukhaireni Rural Municipality-6, Devghat Rural Municipality-4 and 5 will be acquired. Forty-three per cent of the construction work has been completed in a period of four years since the beginning of the project.

According to Kiran Kumar Shrestha, managing director of Tanahun hydropower limited, the promoting company of the Tanahun hydropower project, under package one, 25 per cent of the construction of the dams has been completed, under package two, 45 per cent of the construction of the power house, and under package three, 69 per cent of the physical work.

Under package one, Song Da Corporation, Vietnam and Kalika Construction Pvt. Ltd. Nepal JV are jointly constructing 140 metres high embankments. For the construction of the main dam, work required for diverting the river like the construction of diversion tunnels, the digging of the slope of the upper part of the dam and upgrading the entrance road is underway, said the project chief Rajbhai Shilpakar.

Syno Hydropower, China’s Sinohydro is constructing the tunnel, the power house. Similarly, it supplies, installs and operates hydro mechanical and electro-mechanical equipment. The project aims to be completed within the Nepali month of Asar, 2083 BS. Under package one, the project was contracted with the Song Da Corporation, Vietnam and Kalika Construction Pvt. Ltd. Nepal JV on 22 March 2021 at the cost of over Rs 21.66 billion.

Under this package, for the construction of the main dam, the construction on the diversion tunnels one and two required to diver the river is underway said the project. Digging from the inlet and outlet of both the diversions is ongoing, said the project.

As part of the digging of the slope of the upper part of the main dam, digging the land from 544 to 480 metres has been completed. The construction of the access road to dig the slope of the upper part on the right part of the banks of the rover has been affected due to rain.

For the construction under package two, Sinohydro on 1 October 2018 reached an agreement at the cost of USD 1.1 billion.

Under this package, constructing the underground powerhouse with 89 metres in length, 22 metres in width and 51 metres in height was over on 24 June 2022. In addition, constructing the main access tunnel, cable tunnel and the access tunnel leading to the dam from the right side of the Seti River and the tank has been over, said the project chief Shilpakar

Source: RSS