Tag: Rahughat Hydropower Project
Rahughat Hydropower Project Resumes 20 MW Generation After Flood Repairs
Kathmandu, October 8, 2026: Power generation has resumed at the Rahughat Hydropower Project after repair and maintenance works were completed within 11 days following...
Flood-hit hydropower projects in Seti-Madi, Marsyangdi corridors resume operation
KATHMANDU: Hydropower projects along the Seti-Madi and Marsyangdi corridors that were disrupted by floods have resumed operation. According to the Nepal Electricity Authority (NEA),...
Rahughat Hydropower Project Reaches Test Production After 15 Years
Myagdi: Nearly a decade and a half after construction began, the long-awaited 40 MW Rahughat Hydropower Project in Myagdi has entered the test production...
Hydropower Projects Drive Surge in Forest Revenue
Kathmandu: Revenue collected by the Division Forest Office has increased more than fourfold after hydropower and transmission line projects paid higher fees for the...
Nepal’s Energy Sector, Progress Under the Government’s First 100 Days
In its first 100 days in office, the government has placed the energy sector at the centre of its economic transformation agenda, introducing a...
Rahughat 220 kV Switchyard Operational, 127.8 MW Connected to National Grid
Myagdi: A 220 kV switchyard constructed at Tilkenichaur in Raghuganga Rural Municipality–3, Myagdi, has come into operation. With the commissioning of the switchyard, 127.8...
Final Phase of 40 MW Rahughat Hydropower Project Underway
June 1st, Kathmandu — The construction of the 40-megawatt Rahughat Hydropower Project has reached its final stage. Raghu Ganga Hydropower Limited, a subsidiary of...
Rahughat Hydropower at Risk: Authorities Assess Landslide Prevention Measures
MYAGDI, March : Nepal Electricity Authority's subsidiary, Raghu Ganga Hydropower, is constructing the 40 MW Rahughat Hydropower Project, whose dam faces the risk of...
Eleven hydropower projects are being constructed in three rivers of Myagdi,...
Myagdi — Eleven hydropower projects are under construction in Myagdi Khola, Rahughat, and Mistri Khola. Once these projects are completed, an additional 390 megawatts...
Rahughat Hydropower Project Advances with New Pressure Shaft Installation
Myagdi (Beni), May 24: The 'Pressure Shaft' of the 40 MW Rahughat hydropower project under construction in Raghuganga Rural Municipality of Myagdi has been connected.
According...