Tag: Nepal Electricity Authority
Damauli–Bharatpur Transmission Line Nears Completion, 82% Work Done
Construction of the 220 kV double-circuit Damauli–Bharatpur transmission line for the 140 MW Tanahu Hydropower Project, currently under construction in Tanahu, has gained momentum....
India Extends Export Approval for 96.5 MW from Four Hydropower Projects
Kathmandu — India has renewed approval for the export of 96.50 MW of electricity from four hydropower projects in Nepal. The projects whose export...
Matatirtha–Chobhar 132 kV Transmission Line Completed, Easing Power Supply in Kathmandu...
Kathmandu, 6, October 2026,— Construction of the Matatirtha–Chobhar section of the Thankot–Chapagaun–Bhaktapur 132 kV Transmission Line Project, considered crucial to strengthening the electricity supply...
RCOD Extended for 27 Hydropower Projects with a Combined Capacity of...
Kathmandu. Following the initiative of Energy, Water Resources and Irrigation Minister Biraj Bhakta Shrestha, the Nepal Electricity Authority (NEA) has extended the scheduled date...
Minister Shrestha Directs NEA to Expand Digital Electricity Bill Payments
Kathmandu. Energy, Water Resources and Irrigation Minister Biraj Bhakta Shrestha has directed the Nepal Electricity Authority to systematize the digital payment system for electricity...
Hetauda–Dhalkebar 400 kV Transmission Line Reaches Final Stage
Kathmandu: The construction of the Hetauda–Dhalkebar 400 kV transmission line, which has remained stalled for the past 12 years, has reached its final stage....
Energy Ministry Moves to Remove Hurdles, Expedite 12 Transmission Line Projects
Kathmandu, Oct. 3: The Ministry of Energy, Water Resources and Irrigation has started coordinating to remove obstacles affecting the construction of transmission lines currently...
Transmission charge for national grid fixed at Rs 413,000 per MW
Kathmandu: The Electricity Regulatory Commission (ERC) has determined the transmission charges for using the national electricity transmission grid operated by the Nepal Electricity Authority...
NEA Schedules Power Cuts Across Kathmandu Valley From October 1–12 for...
KATHMANDU — Electricity supply will be disrupted at various locations in Kathmandu Valley to facilitate the operation of the underground electricity distribution system and...
Floods, Landslides Disrupt Power Generation at Mistri Khola and Daram Khola...
KATHMANDU: Floods and landslides have caused greater damage to transmission infrastructure than to the generation structures of hydropower projects, disrupting electricity generation and transmission...