Powering Progress: Successful Test Run of Nilgiri Khola-2 Transmission Line

MYAGDI, Feb 9: The test run of the transmission line of the 71MW Nilgirikhola-2 Hydropower Project has been successfully conducted. The project is based...

Thulo Khola Hydropower Project to Start Generating Electricity Within 8 Months

KATHMANDU, Dec 10: The 21.3 MW Thulo Khola Hydropower Project completed construction of its tunnel on Saturday. According to the project, the 2,700 meter long tunnel...

Disregard for Safety Measures Claims Lives of Myagdi’s Hydropower Workers

Myagdi district has seen a rise in the number of new hydropower projects of late. However, the increase in the number of projects has...

Powering Progress: Khurkot-New Butwal Transmission Line Enters Testing Phase

The Khurkot-New Butwal section of the Khurkot-New Butwal Transmission Line has been successfully tested. Following the completion of the section under the 220kV national...

Eighteen hydropower projects under construction in Myagdi

Eighteen hydropower projects are under construction in Kaligandaki, Raghuganga, Myagdi and various tributaries flowing from Myagdi. The target is to generate 662 MW of...

Mistri Khola Hydro Project To Generate Power In A Month

December 24, 2020 Myagdi: The 42-MW Mistri Khola hydropower project has stepped up its preparation to generate power within a month. Based in Annapurna-4, Narchyang of...

BHEL bags order for second hydroelectric project order in Nepal

Last year, it had won an order for the largest hydropower project in Nepal, 900 MW Arun-3 HEP, which is presently under construction February 03,...