Tag: Budhiganga hydropower project
Budhiganga Hydropower Project Faces Contract Delays
Achham — It has been nearly three decades since the study began for the 20-megawatt Budhiganga Hydropower Project, which was proposed to be constructed...
Budhiganga Project Stalled in Preparatory Phase
Kathmandu: The Budhiganga Hydropower Project, originally targeted for completion in 2025, is now expected to take another four years to finish. Although the contract...
Budhiganga Hydropower Project Left Out of Government Priorities
Achham — Government negligence, the silence of those representing Achham and leading the district, and foreign donors refusing agreements under various pretexts to suit...
A Vision for Energy Transformation: Achieving 28,500 Megawatts in 10 Years
The government has set an ambitious goal of increasing electricity capacity to 28,500 megawatts within 10 years. If this target is achieved, there is...
Budhiganga Hydel’s tender process in limbo
The much-hyped 20-Megawatt Budhiganga hydropower project has not been able to complete its tender process, which has hindered progress.
The project called international tenders for...
Construction of Budhiganga hydropower project has not started yet
Achham - The Budhiganga hydropower project, which is seen as the proud project of the Far West, has not been able to proceed with...