MCC Awards First Construction Contract: New Butwal Substation to be Completed in 39 Months

May 10, 2024
1308
Share
Facebook
Twitter
WhatsApp
Email
Print

    NAWALPARASI, May 9: The Millennium Challenge Account Nepal (MCA-Nepal) has inked a pivotal contract with Linxon India Pvt Ltd for the construction of the 400 kV New Butwal Substation in Nawalparasi (Bardaghat Susta West) district, Lumbini Province.

    The 400 kV Gas Insulated Switchgear (GIS) substation will be constructed within the contract duration of 39 months.

    The signing ceremony was attended by dignitaries including Kulman Ghising, Managing Director of Nepal Electricity Authority (NEA), and US Ambassador to Nepal, Dean R Thompson.

    Ambassador Thompson reaffirmed the US government’s dedication to collaborating with Nepal to meet its energy needs, emphasizing the pivotal role of the 400 kV New Butwal Substation in fostering cross-border energy trade and bolstering economic growth.

    He said, “The 400 kV New Butwal Substation will improve Nepal’s transmission capacity, contributing to reliable and affordable electricity for household consumption, expanded commercial and industrial enterprises and cross-border electricity trading.”

    NEA Managing Director Ghising said, “The 400 kV substation has been a priority for the NEA and will supplement the existing 220 kV substation to significantly increase cross-border energy trade in the region.”

    During the event, MCA-Nepal Executive Director Khadga Bahadur Bisht highlighted the overall progress being made in the implementation of the MCC Nepal Compact, stating “MCA Nepal is expediting all works for the construction of the transmission lines and substations under the Electricity Transmission Project. We are in the final stages of the procurement process to sign the contract for the construction of the remaining two substations as well.”

    The New Butwal Substation is part of the Electricity Transmission Project, funded by the US government’s Millennium Challenge Corporation (MCC) and the Government of Nepal, aimed at fortifying Nepal’s energy infrastructure. Additionally, MCA-Nepal is spearheading the construction of two other substations – one in Ratmate, Nuwakot district, and the other in Damauli, Tanahun district – further bolstering the nation’s energy grid.

    With the 18km Nepal portion of the New Butwal-Gorakhpur power transmission line set for advancement, Nepal is poised to facilitate timely initiation of cross-border power trade as outlined in the agreement with India.

    Source: Republica

    Share
    Facebook
    Twitter
    WhatsApp
    Email
    Print
      Previous articlePeace Energy Secures Financing for Upper Kabeli Hydropower Project: Tesla Hydro USA Leads Investment
      Next articlePower Import Deal with Nepal Finalized, Confirms FM
      OnlineNEF@Nepal

      RELATED ARTICLESMORE FROM AUTHOR

      News

      IPPAN Urges Government Action to Safeguard Hydropower Investments

      News

      Minister Ghising: Electric Vehicle Charging Stations Can Generate Jobs for Youth

      News

      NEA Signs PPAs for 24 Solar Projects Worth 355 MW

      My Tweets

      Subscribe via Email

      Enter your email address to subscribe and receive notifications of new posts by email.

      Join 8,739 other subscribers

      MOST POPULAR

      माथिल्लो तामाकोसीको ३७ प्रतिशत काम पूरा – प्रगतिमा कोष सन्तुष्ट

      October 18, 2012

      लगानी बोर्डले अगाडि बढाएका पाँच वटा जलविद्युत् आयोजना समस्याग्रस्त , प्रमुख...

      July 18, 2017

      Reservoir filling starts at Neelum Jhelum

      October 20, 2017

      Arun III Hydropower Project about 15 percent complete

      January 21, 2019
      Load more

      HOT NEWS

      News

      Chinese company withdrawing from hydropower projects due to lack of market...

      मन्त्री जनार्दन शर्माकाे अाश्वासन, अब जतिखेर पनि बिजुली

      Article

      Unleashed Greed, Burning Earth: How Capitalism Fuels the Climate Crisis

      Sindhuli leaders agree to not obstruct transmission line project

      An independent forum and an on-line channel for the Nepal energy markets(Hydropower, Wind, Biomass, Solar, Petroleum).
      Contact us: info@nepalenergyforum.com

      POPULAR POSTS

      NEA Electricity tariff rates

      July 16, 2023

      China’s Mega-Dam on the Yarlung Tsangpo: Geopolitical and Environmental Alarm

      December 28, 2024

      Water Clouds on the Tibetan Plateau

      May 12, 2016

      POPULAR CATEGORY

      • News3000
      • Article239
      • International105
      • Infrastructure35
      • Interview18
      • Events9
      • Notice9
      • Press Release4
      © NEF Online Pvt. Ltd