283 MW Upper Tamor Project to Use TBM Machines for Excavation
Taplejung — In Phaktanglung Rural Municipality, the excavation of the 283 MW Upper Tamor Hydropower Project, which is part of the 285 MW Upper...
Rahughat Hydropower at Risk: Authorities Assess Landslide Prevention Measures
MYAGDI, March : Nepal Electricity Authority's subsidiary, Raghu Ganga Hydropower, is constructing the 40 MW Rahughat Hydropower Project, whose dam faces the risk of...
Kabeli-3 Hydropower Project to Begin Production by Mid-March
Taplejung - The 21.93 MW Kabeli-3 Hydropower Project is set to begin production within the mid week of March. According to project officials, construction...
Rs 29.5 Billion Investment Secured for Kaligandaki Gorge Hydropower Project
KATHMANDU, March 8: Laxmi Sunrise Bank and the co-financing partner banks have signed an agreement with Kaligandaki Gorge Hydropower to invest in the 180-megawatt...
Power Transmission Pole Installation in Full Swing in Butwal
Kathmandu, Mar. 8: The work on installing monopoles for the transmission line on the road section from Yogikuti Chowk to Horizon Chowk in Kalikapath...
NEA Honors Municipalities for Clearing Street Light Dues
Kathmandu, Mar. 7: The Nepal Electricity Authority has honoured the municipalities under Lumbini Province that have paid their street light dues.
Municipalities and rural municipalities...
NEA MD Ghising Inaugurates 33 kV Double Circuit Line in Kapilvastu
KATHMANDU, March : Nepal Electricity Authority (NEA) Managing Director Kulman Ghising has inaugurated the 33 kV double circuit transmission line from Motipur to Taulihawa...
Construction Begins on Mid-Kaligandaki Hydropower Project
MYAGDI, March : Construction of 66.3 MW Mid Kaligandaki Hydropower Project has begun in Annapurna Rural Municipality of Myagdi.
The Rusuwa Multi JV, a contractor...
Pure Energy Limited Opens IPO for Project-Affected Locals and Nepali Workers Abroad
KATHMANDU, March 4: Pure Energy Limited has issued an initial public offering (IPO) for locals in the affected areas and for the Nepali workers...
Upper Rahughat Hydropower Project Nears Completion, Set to Generate 48.5 MW by July 2025
MYAGDI, March 4: The 48.5 MW Upper Rahughat Hydroelectric Project, located on the Rahughat River flowing through Raghuganga Municipality of the district, has entered...