Upper Trishuli 3A deadline likely to get extended

    1085

    NUWAKOT, FEB 8:

    upper trishuli-1The deadline for the completion of 60 megawatts Upper Trishuli 3A is likely to be extended as the project is unlikely to complete within the given deadline.

    According to Sher Singh Bhat, deputy managing director of Nepal Electricity Authority (NEA), the government is preparing to extend the deadline for the project and increase the project cost.

    “It is not possible to complete the project within three months so there is no option other than to extend the project deadline,” he said. The project will be completed by May 2014. Bhat said that it would take 26 months to complete the 60-megawatts project.

    “The locals have provided their land with a hope that the project will be completed,” a local Shesh Nath Bhatta told Republica.

    Source : Republica