Tag: Dam construction
Tanahun Hydropower Expands Community Works, Completes 96 Infrastructure Schemes
The 140 MW Tanahun Hydropower Project under construction at Jhaputar, Rishing Rural Municipality-1, is implementing seven development schemes in the affected areas under its...
Tanahun Hydropower Main Dam Construction Reaches 50% Completion
Damauli — Construction of the main dam of the under-construction Tanahu Hydropower Project in Rishing Rural Municipality of Tanahun district has gained momentum.
Under Package...
273 MW Lower Badigad Hydropower Project Gains Momentum Boosting Regional Development
Resunga (Gulmi), May 5: A long-discussed plan to harness the hydropower potential of the Badigad River is finally moving forward, bringing renewed hope and...
Kali Gandaki Hydropower Project Cost Slashed to NPR 225B
Kathmandu: The cost of the Kali Gandaki reservoir-based hydropower project is projected to decrease. The environmental impact assessment (EIA) report, along with recommendations, has...
Tanahun Hydropower: Tree Marking Starts for 220kV Damauli–Bharatpur Line
Kathmandu. Tree marking has begun in forest areas required for the construction of the transmission line under the Tanahun Hydropower Project. According to Project...
Land Acquisition Begins for 126 MW Lower Seti Hydropower Project in...
Tanahun: Land acquisition has begun for the 126 MW Lower Seti Hydropower Project, which is set to be constructed in Tanahun district.
The project will...
Construction Begins on Access Road for 126 MW Lower Seti Hydropower...
Damauli (Tanahun): Tanahun Hydropower Limited is set to begin construction of an access road for the 126-megawatt Lower Seti Hydropower Project. The company, which...
Rahughat Hydropower Project: Tunnel Structure Ready, 92% Physical Progress Achieved
Myagdi: The construction of the main structures inside the tunnel under the 40-megawatt Rahughat Hydropower Project being built in Myagdi has been completed. This...
Budhigandaki ‘A’ and ‘B’ Hydroelectric Projects: Construction Preparations Underway
Gorkha: Preparations have been advanced for the construction of two large hydroelectric projects based on the Budhigandaki River in Gorkha. The Budhigandaki ‘A’ Hydroelectric...
Upper Myagdi-1 Hydropower Project Hits 30% Milestone
The Upper Myagdi-1 Hydropower Project has achieved 30 percent physical progress.
The construction of the dam, tunnel, and powerhouse is moving forward at...