New Damauli-New Butwal 400 kV Line Begins Construction Amid Deadline Concerns

96

Kathmandu: The Millennium Challenge Account Nepal (MCA-Nepal) has announced the commencement of construction of the New Damauli-New Butwal 400 kV double-circuit transmission line, which passes through Tanahun and Palpa districts. Construction of the 90-kilometre section officially began on November 20, 2026. The project involves the construction of approximately 250 towers, with the transmission line extending through Tanahun, Palpa, Nawalparasi (Bardaghat Susta East) and Nawalparasi (Bardaghat Susta West) districts.

According to MCA-Nepal, the transmission line is an important section of the 315-kilometre 400 kV transmission network being built under the MCC Nepal Compact. However, when the construction start date, contract duration and the Compact’s implementation deadline are considered together, questions arise about whether the project can be completed within the stipulated timeframe.

42-Month Contract, but Construction Begins Only in November 2026

The contract for the construction of the New Damauli-New Butwal transmission line was awarded to Waiba-Salasar JV. According to MCA-Nepal’s contract award notice, the contract was awarded on August 8, 2025. The contract period is 42 months from the date of commencement of work.

The contract amount is US$74,953,233. It also includes provisional work worth US$2,074,686, which MCA-Nepal may use at its discretion. Both amounts exclude value-added tax (VAT).

MCA-Nepal’s March 2026 progress report stated that the detailed design of the New Damauli-New Butwal section was under review. The report listed the contract amount for the 90-kilometre transmission line at US$77,020,000. This figure is broadly consistent with the combined total of the base contract amount and provisional work mentioned in the contract notice.

However, the fact that the project was still at the detailed design review stage in March 2026 and construction was announced only in November 2026 raises questions about the actual construction schedule and progress management.

Contract Period Extends Beyond the Compact’s Original Deadline

The MCC Nepal Compact came into force on August 30, 2023. Under the agreement, its original implementation period is five years, ending on August 30, 2028.

The contract period for the New Damauli-New Butwal transmission line, however, is 42 months from the commencement of work. If November 20, 2026, the publicly announced construction start date, is considered the formal contract commencement date, the 42-month period would extend into 2030, well beyond the Compact’s original deadline.

However, it is unclear whether the publicly announced construction start date and the formal contract commencement date are the same. Therefore, the actual contract commencement date, the scheduled completion date and any revised deadline for the Compact need to be officially clarified.

Although MCA-Nepal’s contract award notice specifies a 42-month period, publicly available information does not explain how this duration has been accommodated within the Compact’s original implementation deadline.

Contracts for Three Transmission Line Sections Exceed US$230 Million

According to MCA-Nepal’s March 2026 progress report, the 315-kilometre transmission network has been divided into three main sections, with separate contracts awarded for each.

  • Lapsiphedi-Ratmate-New Hetauda (117 km): US$76.65 million
  • Ratmate-New Damauli (90 km): US$76.52 million
  • New Damauli-New Butwal (90 km): US$77.02 million

The combined contract value of the three sections amounts to approximately US$230.19 million. All amounts exclude VAT.

Ensuring timely progress on detailed design reviews and construction across all three transmission line sections remains a challenge. A delay in one section could affect the operation of the entire transmission network, even if construction of the other sections is completed.

Foundation Sites for Only 132 Towers Secured by March

According to MCA-Nepal’s March 2026 progress report, foundation sites for 132 transmission towers had been secured across 10 districts. The same report stated that forest clearance had been obtained for Nawalparasi (Bardaghat Susta West), while forest approval processes were still underway in the remaining districts.

Issues such as the use of forest land, tree felling, access to land, local consent and compensation distribution can affect construction schedules. Timely completion of these processes along the 315-kilometre transmission line route is essential to maintaining construction momentum.

MCA-Nepal has also stated that a livelihood restoration programme is being implemented for approximately 1,500 affected people. In addition, 270 people have received training through the programme in the Ratmate substation area.

2025 US Aid Suspension Also Affected the Timeline

Implementation of the MCC Nepal Compact faced interruptions in 2025 due to a review of US foreign assistance. Activities under the Compact were affected for some time as a result of the US government’s aid review process. Although a decision was subsequently made to continue the programme, the interruption affected the project’s implementation schedule.

Reports have also emerged of discussions between Nepal and the United States on extending the Compact’s duration. However, with the original deadline set for August 2028, additional time may be required to complete the projects.

An extension of the Compact could provide additional time for project completion. However, clear information is needed regarding the formal decision to extend the agreement, the length of any extension and the associated financial arrangements.

Completing the Transmission Line Is Not the Only Challenge

Once completed, the New Damauli-New Butwal transmission line is expected to help connect electricity generated by hydropower projects under construction, as well as future projects, across different river basins to the national transmission system. It could facilitate the domestic flow of electricity and contribute to expanding electricity trade with India.

However, completing a transmission line and operating it at full capacity are two different matters. Substations, other transmission line sections, coordination with the national grid, testing and operational approvals must also be completed on time.

MCA-Nepal needs to regularly publish progress updates on the New Damauli-New Butwal section, for which it has announced the start of construction. In particular, making public the formal contract commencement date, progress on tower foundations, tower erection, conductor stringing, forest and land acquisition status, and the revised completion schedule would make it possible to assess the project’s actual progress.

The question of how the gap between the 42-month contract period and the Compact’s original August 2028 deadline will be managed has now become increasingly important as construction of this transmission line moves forward.

 