May 1st, Myagdi – A 37.5-megawatt capacity hydropower project named Chimkhola–Mangale–Rahughat Hydropower Project has been constructed in Raghuganga Rural Municipality of Myagdi.
The project, promoted by Tudi Power Company Limited, has stated that it will begin test production within the next 15 days.
According to the project’s resident engineer, Prakash Timilsina, equipment has been installed at the powerhouse, and the transmission line is also ready.
A 14-kilometer long, 220 kV capacity transmission line has been constructed to transmit the electricity produced by the project to the national grid.
This is the first hydropower project constructed in the Rahughat basin.