West Seti–New Attariya 400 kV Line to Be Built, Capable of Carrying 1,500 MW

33

Kathmandu: The West Seti–New Attariya (Daiji) 400 kV Transmission Line Project is set to be built in Sudurpashchim Province. Rastriya Prasaran Grid Company Limited (the National Transmission Grid Company) will build the line.

Through a public notice, the company has asked stakeholders to submit written comments and feedback to the Department or the promoter company within 35 days of the notice’s publication if they believe the line’s construction and operation would cause significant adverse environmental effects, such as soil erosion, floods or air pollution, under Section 24 of the Electricity Act, 1992 AD.

Under the project, the transmission line will run from the proposed West Seti substation in Doti district through Jorayal Rural Municipality in Doti, and Parshuram Municipality, Alital Rural Municipality and Ganyapadhura Rural Municipality in Dadeldhura, to the New Attariya (Daiji) substation proposed by the Nepal Electricity Authority in Bedkot Municipality-2, Kanchanpur.

The 68-kilometer line will be a 400 kV double-circuit line, capable of transmitting up to 1,500 megawatts of electricity.

A total of 157 towers will be built for the project. The maximum tower height will be 51.43 meters, and the distance between towers will range from 149.023 meters to 839.086 meters.

The project will require a total of 312.35 hectares of land: 19.97 hectares for the towers and substation area, and 292.08 hectares for the transmission line’s right of way (RoW).

The right of way will cover a total width of 46 meters, extending 23 meters on each side of the line’s centerline.

The project aims to complete construction within two and a half years. It has stated that work during construction and operation will be carried out with attention to environmental impacts, including soil erosion, floods and air pollution.