Rapid Progress in 46.25 MW Upper Myagdi Hydropower Project

Kathmandu: The Upper Myagdi Hydropower Project under construction in Dhaulagiri Rural Municipality of Myagdi is progressing faster than expected. Within just 13 months of...

Sabha Khola ‘B’ Hydropower Project Completes 4,110-Meter Main Tunnel

Kathmandu. The construction of the main tunnel of the 21.5-megawatt Sabha Khola “B” Hydropower Project, being built in Sabhapokhari Rural Municipality of Sankhuwasabha, has...

Nupche–Likhu Hydropower Project 93.8% Complete, Final Works Underway for COD

Kathmandu-  The 57.5 MW capacity Nupche-Likhu Hydropower Project under construction in Ramechhap district has been physically completed 93.83%. According to the latest progress report...

Rahughat Hydropower Project: Tunnel Structure Ready, 92% Physical Progress Achieved

Myagdi: The construction of the main structures inside the tunnel under the 40-megawatt Rahughat Hydropower Project being built in Myagdi has been completed. This...

Final Stage of Pipeline Installation Achieved in Rahughat Hydropower Tunnel

Myagdi: The pipeline installation work in the tunnel of the 40-megawatt Rahughat Hydropower Project, under construction in Rahuganga Rural Municipality, Myagdi, by Nepal Electricity...

Deforestation Surges Ahead of Upper Arun Project Construction

Kimatanka (Sankhuwasabha) — More than two thousand trees have been cut down for the construction of the 1,063-megawatt Upper Arun project, which is set...

Construction Begins on Access Road for Mudikhola Hydropower

Myagdi – in Dhaulagiri Rural Municipality-4 of Myagdi, construction of the access road for the 14-megawatt Mudikhola Hydropower Project has begun. At the confluence of...

Upper Myagdi-1 Hydropower Project Hits 30% Milestone

The Upper Myagdi-1 Hydropower Project has achieved 30 percent physical progress. The construction of the dam, tunnel, and powerhouse is moving forward at...

After a Decade and a Half, Middle Bhote Koshi Starts Power...

After a decade and a half of struggle, the Middle Bhote Koshi Hydroelectric Project has started commercial production of 102 megawatts of electricity. ...

Construction of Tamakoshi Fifth and Rolwaling Projects Stalled

Dolakha — Construction work on two hydropower projects being built with domestic investment has been halted for the past three months due to delays...