Tree-Cutting Order for Dadakhola–Rahughat Transmission Line Implemented After Two-Year Delay

Kathmandu: The Cabinet decision to allow the use of community and national forest areas for the 132 kV Dadakhola–Rahughat transmission line project under construction...

Nepal Strengthens Energy Infrastructure as Capacity Reaches 4,296 MW

Kathmandu — Nepal’s total installed power generation capacity has reached 4,296 MW. According to the Ministry of Energy, Water Resources and Irrigation, the figure...

132 kV Burtibang Substation Comes into Operation

Dhorpatan: The 132 kV substation constructed in Burtibang, Baglung, has come into regular operation. The substation was completed on February 14 and tested on...

EIA Process Begins for 328-MW Bharbung Hydropower Project in Dolpa

Kathmandu. In Dolpa, which has recently been considered lagging behind in development and prosperity, a 328-megawatt Bharbung Hydropower Project is set to be constructed....

400 kV West Seti Line: Public–Private Partnership Process Restarted

Kathmandu. The National Transmission Grid Company Limited has once again invited expressions of interest from the private sector for the construction of a 400...

Budhigandaki ‘A’ and ‘B’ Hydroelectric Projects: Construction Preparations Underway

Gorkha: Preparations have been advanced for the construction of two large hydroelectric projects based on the Budhigandaki River in Gorkha. The Budhigandaki ‘A’ Hydroelectric...

Dadakhet–Raughat Transmission Line Achieves 70% Progress in Five Years

Myagdi: The Dadakhet–Raughat 132 kV transmission line project, which was launched to connect the electricity generated from the hydropower projects in the Myagdi and...

Seven Power Grid Substations Shift to Automated Operation

Seven old grid substations of the Nepal Electricity Authority have come into operation under an automated system. The automated system is expected to...

Substation Construction Picks Up Pace in Marchawar Region

Lumbini (Marchawar), Jan 27: Almost 40 percent of the work of electricity substation being constructed in Marchwar area of Rupandehi has been completed. Nepal Electricity...

Dhara Pani 220 kV Substation Under Construction, Khudi in Final Stages

Kathmandu, November 8, 2024 – A 220 kV capacity substation is under construction in Dharapani, Nasong Rural Municipality-1, Manang, as part of the Marsyangdi...