Dadakhet–Raughat Transmission Line Achieves 70% Progress in Five Years

Myagdi: The Dadakhet–Raughat 132 kV transmission line project, which was launched to connect the electricity generated from the hydropower projects in the Myagdi and...

Construction Begins on Access Road for Mudikhola Hydropower

Myagdi – in Dhaulagiri Rural Municipality-4 of Myagdi, construction of the access road for the 14-megawatt Mudikhola Hydropower Project has begun. At the confluence of...

Upper Myagdi-1 Hydropower Project Hits 30% Milestone

The Upper Myagdi-1 Hydropower Project has achieved 30 percent physical progress. The construction of the dam, tunnel, and powerhouse is moving forward at...

Five Hydropower Projects with 162 MW Capacity Underway in Single Ward

Myagdi — Five hydropower projects with a total capacity of 162 megawatts have been constructed on the river flowing through Narchyang, located in Annapurna...

Rahughat Project Gets Another Deadline Push, Marking Third Extension

Myagdi, July 18: The deadline for Rahughat Hydropower Company being constructed in Myagdi has been extended for the third time. The 40-megawatt under-construction project is...

Final Phase of 40 MW Rahughat Hydropower Project Underway

June 1st, Kathmandu — The construction of the 40-megawatt Rahughat Hydropower Project has reached its final stage. Raghu Ganga Hydropower Limited, a subsidiary of...

Chimkhola–Mangale–Rahughat Hydropower Project Ready for Test Production

May 1st, Myagdi – A 37.5-megawatt capacity hydropower project named Chimkhola–Mangale–Rahughat Hydropower Project has been constructed in Raghuganga Rural Municipality of Myagdi. The project, promoted...

NEA Myagdi Completes Electrification of Punhill

Myagdi, Apr. 9: The extension of electricity services to Punhill, a popular tourist destination in Annapurna Rural Municipality-6 of Myagdi district, has made it easier...

Construction Begins on Three Hydropower Projects in Myagdi, Adding 155 MW...

Myagdi (Beni), Feb 22: Construction of three hydropower projects has begun in Mudi, Dhaulagiri Rural Municipality-4 of the district.Construction of three hydropower projects with...

Halfway Through: Dandakhet-Rahughat Transmission Line Project Lagging Behind Schedule

September, Myagdi. The construction of the 132 kV capacity Dandakhet-Rahughat transmission line project, currently being built by the Nepal Electricity Authority in Myagdi, has...