Nepal Secures Approval to Import 350 MW of Electricity from India During Winter

96

Kathmandu, November 17, 2026: Nepal Electricity Authority (NEA) has received approval to import 350 megawatts (MW) of electricity from India during this year’s winter season.

India’s Central Electricity Authority (CEA), under the Ministry of Power, has authorised the NEA to purchase electricity at competitive rates from the Day-Ahead Market and Real-Time Market of the Indian Energy Exchange (IEX) for up to 17 hours a day.

The approval allows Nepal to import electricity from November 17, 2026, to July 31, 2027. Under the arrangement, electricity can be imported through IEX at any time except between 5 am and 8 am and between 5 pm and 9 pm daily.

According to the approval, Nepal can import 300 MW through the 132 kV Kataiya-Kusaha, Ramnagar-Surajpura and Raxaul-Parwanipur transmission lines. An additional 50 MW can be imported through the 132 kV New Nautanwa-Mainahiya transmission line, bringing the total approved import capacity to 350 MW.

NEA Managing Director Dirghayu Kumar Shrestha said the approval to import 350 MW from India would make it easier to manage electricity demand and supply during the upcoming winter season.

Shrestha said preparations were underway to manage electricity demand and supply, taking into account the damage to hydropower projects and transmission lines caused by the flash flood that originated in the Bhotekoshi River in Rasuwa and affected the Trishuli River basin. As a result, hydropower projects with a combined installed capacity of 431 MW have been disconnected from the national electricity system.

An analysis based on last year’s electricity demand and generation patterns suggests that domestic electricity production will fall short of demand for four months, from December 2026 to March 2027.

During this period, Nepal is expected to rely on electricity imports from India. In particular, average daily imports of 450 to 500 MW are projected throughout January and February 2027.

During peak demand hours, Nepal may need to import as much as 800 to 900 MW of electricity daily. Import requirements are expected to be relatively lower in December 2026 and March 2027.

From April 2027 onwards, river flows are expected to gradually increase, boosting domestic electricity generation. This is expected to reduce the need for imports and allow Nepal to resume electricity exports.

NEA Gets Approval to Export 56 MW of Electricity

The NEA has also received approval to sell a total of 56 MW of electricity generated by three hydropower projects in the Indian Energy Exchange (IEX).

The authority will be allowed to export the electricity from November 17, 2026, to July 31, 2027.