Compensation Fixed for Households Affected by Tanahun Hydropower Project
Tanhun — Compensation has been determined for 10 households affected by the under-construction 140-megawatt Tanahun Hydropower Project in Jhaputar, Rishing Rural Municipality-1.
According to the...
VUCL, NEAEC Sign Agreement for DPR and IEE of Dullu–Malika Solar Project
Kathmandu. An agreement has been signed between "Electricity Generating Company Limited" - Vidyut Utpadan Company Limited (VUCL) and NEA Engineering Company (NEAEC) to carry...
Mewa Khola prepares for trial generation after completing internal testing
Kathmandu. The 50-megawatt Mewa Khola Hydropower Project, completed on the Mewa Khola in Taplejung, has finished its internal testing and is now preparing for...
NEA Moves Ahead with Land Acquisition for Damauli 220 kV Transmission Project
Pokhara: The Nepal Electricity Authority has moved forward with the process of permanently acquiring land required for the construction of transmission line towers in...
Karnali Moves to Resolve Overload and Low-Voltage Problems with 132 kV Line
Kathmandu, Feb 2: A 132-kV transmission line has come into operation in Karnali Province, marking the first transmission line operated by the Nepal Electricity...
Construction Begins on Access Road for 126 MW Lower Seti Hydropower Project
Damauli (Tanahun): Tanahun Hydropower Limited is set to begin construction of an access road for the 126-megawatt Lower Seti Hydropower Project. The company, which...
Increasing Power Generation, but No Clear Consumption Strategy: IPPAN President
Kathmandu: Ganesh Karki, President of the Independent Power Producers’ Association of Nepal (IPPAN), has stated that although electricity production is increasing, the state lacks...
325-MW Hydropower Project Approved for Construction in Dolpa
Kathmandu — A 328-megawatt (MW) semi-reservoir hydropower project is set to be constructed in the Himalayan district of Dolpa.
The project, named Bharbung-Tatu Khola Hydropower...
Nupche–Likhu Hydropower Project 93.8% Complete, Final Works Underway for COD
Kathmandu- The 57.5 MW capacity Nupche-Likhu Hydropower Project under construction in Ramechhap district has been physically completed 93.83%. According to the latest progress report...
48.8 MW Khimti-2 Project Moves Ahead Rapidly on Khimti River
Kathmandu: Work is progressing rapidly on the 48.8 MW Khimti-2 Hydropower Project, which is under construction on the Khimti River, flowing along the border...













