132 kV Chobhar Substation Now Operational, Kathmandu Valley Power Supply to Become More Reliable

27

Kathmandu, 29 November 2026: The 132/11 kV Chobhar Substation in Kirtipur Municipality-6 has come into operation. It is considered important for making the Kathmandu Valley’s electricity supply system stronger, more reliable and of better quality. The substation has two 45 MVA power transformers. It receives power through the Matatirtha–Chobhar section, built under the Thankot–Chapagaun–Bhaktapur 132 kV Double Circuit Transmission Line Project.

Nine 11 kV feeder lines have been set up to distribute electricity locally from the substation. Three of these extend toward the Pulchowk area of Lalitpur, and six toward Kirtipur and its surroundings. The feeders are being charged one by one, and supply to local areas has begun.

Nepal Electricity Authority (NEA) Managing Director Dirghayu Kumar Shrestha inspected the substation on Sunday. He instructed the officials concerned to charge the 11 kV feeders immediately and move ahead with transferring the electricity load.

Managing Director Shrestha said the Chobhar Substation will help manage the growing electricity demand, especially in Kirtipur and nearby areas and in Lalitpur’s Pulchowk area. He noted that demand in the Kathmandu Valley rises in winter, so the Matatirtha–Chobhar transmission line and the Chobhar Substation will play an important role in managing supply. For this reason, he directed that the load transfer be completed immediately.

Now that the Chobhar Substation is operating, part of the load currently supplied by the Syuchatar, Teku, Patan and Matatirtha substations will be shifted to Chobhar. This is expected to ease load management at the existing substations and make the Kathmandu Valley’s overall electricity supply system more reliable.

The 132/11 kV substation at Chobhar was built as an alternative arrangement. Work on the Thankot–Chapagaun–Bhaktapur 132 kV transmission line had become difficult in Khokana, Bungamati, Harisiddhi and Lamatar in Lalitpur because of problems acquiring the necessary land and other obstacles.

Construction of an underground 132 kV transmission line of about 4.5 kilometres from the Chobhar Substation to Patan has also been given high priority. A 132 kV substation is also being built in Patan. Once these structures are complete, the Kathmandu Valley’s electricity transmission and distribution system will be further strengthened.

The substation was built on 12 ropani 12 aana of land at Bhutkhel, Chobhar, leased from Himal Cement, which owns it. A Council of Ministers meeting on 31 January 2022, decided to lease the land to the NEA for building the substation. The substation was financed by a concessional loan from the Asian Development Bank (ADB) under its Kathmandu Valley Transmission Capacity Strengthening Project.