Half Finished in 20 Years: Sikta Irrigation Project’s Cost Quadruples

KATHMANDU, July 16: Two decades after construction began, the national pride Sikta Irrigation Project remains only half-complete. Launched in fiscal year 2005/06, the project...

Minister Shrestha Launches Digital Monitoring Portal for National Pride Irrigation Projects

Kathmandu: The Ministry of Energy, Water Resources and Irrigation has launched an integrated digital monitoring portal to enable real-time monitoring of the progress, budget...

Minister Shrestha Urges Timely Completion of Sikta Irrigation Project

Minister for Energy, Water Resources and Irrigation Biraj Bhakta Shrestha has said that all stakeholders must work together to complete the national pride Sikta...

Nepal’s Energy Future: Power Export Expansion Amid Transmission Challenges Ahead of...

Kathmandu: Through the budget for Fiscal Year 2025/26, the government had introduced ambitious programs in the energy, water resources, and irrigation sectors. The government...

Insufficient budget affects Sikta Irrigation Project

Nepalgunj, Apr. 4: The construction work of Sikta Irrigation Project, a national pride project, in Banke has been affected due to lack of budget. Devraj Niraula,...

Complete Sikta irrigation project on time: Minister Pun

November 06, 2019 Minister for Energy, Water Resources and Irrigation Barsha Man Pun has directed the officials of Sikta Irrigation Project— a national pride project...