Tag: NEA
Power Regulatory Body Commits to Granting 50-Year Extensions for Hydropower Project...
KATHMANDU, Feb 23: The director general (DG) of the Department of Electricity Development, Jeebachh Mandal, has said that because the Ministry of Finance (MoF)...
Climate Change Alters Hydroelectricity Production: Impacts and Challenges
KATHMANDU, Feb 23: The production of hydropower projects based on river flow has decreased rapidly in the dry season, posing a challenge to Nepal...
Nepal Steps Closer to Exporting Domestic Power with Bangladesh Deal
KATHMANDU, Feb 22: In a bid to materialize its effort to sell domestically produced electricity to third countries, Nepal is finalizing a deal with Bangladesh.
In...
Renewable Resurgence: Nepal’s Visionary Approach to Power System Enhancement with Solar...
Nepal is seeking consultants to expand its power system, which includes building more than 200 kilometers of new transmission lines, upgrading existing ones, and...
Matatirtha Substation: Powering Kathmandu Valley’s Future with Completion of Largest 220...
With the completion of construction of Matatirtha substation, the Largest 220 kV Substation Kathmandu valley, the quality of distribution system will drastically improve in...
Controversy Erupts Over Non-Bidding Joint Venture Hydel Licensing
Private sector: Proposed legal provision to pick developers will make Nepal more dependent on India on electricity.
A provision in the electricity bill allowing the government to...
Contract Agreement Finalized for 1063-Megawatt Upper Arun Hydropower Project Consultation
Kathmandu, Feb. 16: A supervision consultant has been selected for the 1,063 MW Upper Arun semi-reservoir hydropower project to be built in Bhotkhola Rural Municipality...
Bandarjhula in Chitwan is still in the dark, Nepal Electricity Authority’s...
Kathmandu. Chitwan's Madi municipality-9 Bandarjhula (Hanumanjhula) has not yet received electricity from the national transmission grid.
Nepal Electricity Authority had called for a tender for...
Power Surge: Nepal’s Revenue Soars to Rs 12.40 Billion from Electricity...
KATHMANDU, Feb 9: Nepal sold electricity worth Rs 12.40 billion to India during mid-July and mid-January this year, which was 47.97 percent more than...
Matatirtha Milestone: Kathmandu’s Largest Substation Construction Successfully Completed
Kathmandu, Feb. 7: The construction of 220/132 kV substation at Matatirtha in Chandragiri Municipality of Kathmandu has been completed. Nepal Electricity Authority has constructed...