Tanahun Hydropower: Affected get compensation
Tanahu. Compensation has been provided to 101 families affected during the construction of the Tanahu Hydroelectric Project, a 140 MW capacity project under construction...
400 Families to Receive Compensation for Arun 3 Hydropower Project
Kathmandu — After nearly 80 percent of the construction work of the 900-megawatt Arun 3 Hydropower Project has been completed, around 400 families are...
Commencement of Land Acquisition for Lower Arun Hydropower Project
Sankhuwasabha, Jan. 25: The land acquisition process for the 669-MW Lower Arun Hydropower Project, to be built in the district, has started. The process of...
Govt Moves Forward with Budhi Gandaki Hydropower Project, Establishing Construction and...
The government has started the necessary discussions to decide the structure of construction and financial management of the Budhi Gandaki hydropower project, which is...
Lapsephedi Protests Underscore Difficulties in Nepal’s Infrastructure Development
At least three police personnel were injured as locals hurled stones and over a dozen people allegedly behind the attack were held, Kathmandu district...
Arun 3rd Dam Construction Halted for 58 Days
On the 29th Oct, in Kimathanka (Sankhuwasabha), a protest has been ongoing since last Sep 19th, after the local community did not receive compensation...
Budhigandaki Hydropower Project distributes Rs 28 billion compensation
GORKHA, Feb 13: The national pride project, Budhigandaki Hydropower Project, has distributed a total of Rs 28.18 billion to acquire private land. According to...
नलगाड जलविद्युत् आयोजना : मुआब्जा रकम बढाउन माग
माघ २०, २०७६
जाजरकोट — नलगाड जलविद्युत् आयोजना प्रभावितले जग्गाको मुआब्जा रकम बढाउन माग गरेका छन् । ७ वर्षअघि निर्धारित रकम कम भएको र समयमै नपाइएको...
मुआब्जामै रुमल्लिए कर्णालीका ठूला आयोजना
माघ १५, २०७६
(सुर्खेत) — भेरी बबई डाइभर्सन, माथिल्लो कर्णाली, मध्यपहाडी राजमार्गलगायत राष्ट्रिय गौरवका आयोजना मुआब्जा विवादमै रुमल्लिएका छन् । मुआब्जा विवादकै कारण कर्णालीका ३ ठूला...
Compensation to be reviewed for Budhigandaki hydel project
December 11, 2019
Kathmandu: The government, representatives of different political parties and locals of Gorkha and Dhading districts have reached a four-point agreement on the...