Construction of Chilime-Trishuli Transmission Line in Final Stages
Kathmandu, September 08, 2024: The construction of the Chilime-Trishuli 220 kV transmission line, which is being built to transmit electricity generated from hydropower projects...
Bahrabise Substation Nears Completion, to Connect Madhyabhotekoshi Hydropower
Kathmandu, 4 Feb,2024. The construction of 220-132 KV substation in Bahrabise municipality of Sindhupalchok has reached its final stage. The final phase of the...
The Chinese company’s license to develop the Budhi Gandaki Plant has...
KATHMANDU, April 8: The government has decided to revoke the license issued to the Chinese state-owned China Gezhouba Group Corporation (CGGC) for the development...
Madhya Bhotekoshi Hydropower Project completed 75 percent of construction, with a...
Kathmandu, Oct. 31: The overall construction of the 102 MW Madhya Bhotekoshi Hydropower Project under construction in Sindhupalchowk under the leadership of Chilime Hydropower...
Chinese firm loses substation contract after being no-show
The substations are part of a power line project to bring electricity from Marsyangdi to Kathmandu.