Tanahun: Tree felling has been accelerated in various forest areas of Tanahun and Chitwan for the Damauli–Bharatpur 220 kV transmission line, which is being built under the Tanahu Hydropower Project. According to the project, about 50 percent of the work to remove trees along the transmission line’s route has been completed so far.
According to Project Chief Shyamji Bhandari, trees in the forest areas along the route are being felled after obtaining the required approvals. Trees of various species are being removed mainly in the managed forest in Bharatpur Metropolitan City-1 in Chitwan, the Satanchuli Community Forest, and the Akaladevi and Siddhadevi Community Forests under Bharatpur Metropolitan City-29. In these areas alone, 1,263 trees must be felled.
Under a Council of Ministers decision dated December 6, 2022, approval was granted to use a total of 92.73 hectares of forest land in Tanahun and Chitwan to build the transmission line. Of this approved forest area, 25.27 hectares are in Chitwan and 67.46 hectares are in Tanahun. The government had permitted the removal of a total of 9,127 trees in that forest area.
Construction of the transmission line moved forward after the necessary government approvals were obtained for using the forest area and felling the trees. Project Chief Bhandari said the trees are being cut to clear space for building transmission towers, stringing the wires, and constructing other structures in the forest area.
The contract for the Damauli–Bharatpur 220 kV transmission line, being built under Package 3, was awarded to the Indian company KEC International Limited. A total of 94 towers must be built along the roughly 35-kilometer line.
According to Bhandari, foundations have been completed for 83 of the 94 towers, and 81 towers have been erected. Of the line’s total length of 34.70 kilometers, wire stringing has been completed on 2.2 kilometers so far.
Although tower foundation and erection work has made significant progress, wire stringing needs to speed up along with forest clearance and tree felling. According to the project, the overall physical progress of the transmission line has reached 83.5 percent.
The Damauli–Bharatpur transmission line is considered key infrastructure for connecting electricity from the Tanahu Hydropower Project to the national transmission grid. It is a major part of the infrastructure needed to deliver power from the 140-megawatt project to the national system.
Once tree felling, tower construction and wire stringing in the forest areas are complete, it is expected to become easier to connect the project’s electricity reliably to the national grid.