NEA Targets 650 MW Winter Demand with Eight-Point Power Supply Plan for Kathmandu

Kathmandu: Nepal Electricity Authority (NEA) has prepared an eight-point roadmap to improve the transmission and distribution systems and prevent power cuts in the Kathmandu Valley during the upcoming winter. With peak electricity demand in the Valley projected to reach 650 megawatts (MW), the authority has prioritised expanding transmission capacity, shifting loads between substations and developing alternative power supply routes.

According to the NEA’s Kathmandu Winter 2083 System Strategy, peak electricity demand in the Kathmandu Valley is expected to reach 650 MW this winter. The Valley’s actual peak demand reached 603 MW in fiscal year 2025/26. In the current fiscal year 2026/27, peak demand so far has reached 543 MW, while demand stood at 505 MW as of September 17, according to Munindra Thakur, NEA’s Bagmati Province Chief.

Thakur said the 650 MW peak demand projection for the coming winter takes into account the growing use of electric vehicles, new electricity connections, increased use of electricity for heating and overall growth in demand.

According to Thakur, the available power sources and pooling capacity to supply electricity to the Kathmandu Valley stand at around 700 MW. The system can pool approximately 400 MW through the Matatirtha 220/132 kV system, around 215 MW through the Lamosangu-Bhaktapur 132 kV transmission line and about 60 MW from Kulekhani, bringing the total pooling capacity to 675 MW.

However, the availability of power sources alone is not sufficient. Thakur said the main challenge lies in the capacity of the transmission and distribution network to deliver electricity from these sources through various substations within the Valley to consumers. Accordingly, the NEA has placed maximum utilisation of existing infrastructure and improvements to weak transmission corridors at the centre of its winter strategy.

Matatirtha-Syuchatar-Balaju Corridor Identified as Major Bottleneck

The NEA has identified the Matatirtha-Syuchatar-Balaju 132 kV transmission corridor as a major bottleneck in supplying electricity to Kathmandu. The authority’s strategy states that the capacity of transmission lines and their associated bays, busbars and transformers along this corridor needs to be upgraded.

Similarly, substations at Patan, Chabahil, Bhaktapur, Teku, Baneshwar and K-3 face excessive loading during periods of peak demand. Thakur said the capacity of the upstream transmission network also needs to be increased to supply electricity to newer substations such as Futung and Chapagaun.

A single-line diagram of projected peak winter electricity flows in the Kathmandu Valley, prepared by the NEA, illustrates the flow of electricity between substations including Markichowk 220 kV, Matatirtha, Syuchatar, Futung, Balaju, Teku, Patan, Bhaktapur, Mulpani and Chapagaun. This highlights the importance of not only the infrastructure bringing electricity into the Valley but also the transmission network within it.

Eight-Point Plan to Prevent Load Shedding

The NEA has prioritised eight projects and system improvement measures for implementation before the coming winter.

The first priority is the construction of the Matatirtha-Chobhar-Patan transmission line. Under this plan, the authority aims to develop the Chobhar substation and transmission infrastructure connecting Chobhar to the 132/11 kV Patan substation. This is expected to reduce dependence on the Syuchatar and Balaju corridors and provide an alternative electricity supply route to the southern part of the Valley.

The second measure involves transferring electricity loads from Maharajgunj, Lainchaur and Balaju towards Futung and Chapagaun. The objective is to reduce the load on the Balaju area and improve utilisation of the available transmission capacity.

Likewise, the NEA plans to transfer the loads of Teku and Patan substations to Chobhar, shift the load of Baneshwar to Patan, and redistribute the load of K-3 to Chabahil, Lainchaur, Teku and Baneshwar.

The authority has also prioritised reconductoring both circuits of the Matatirtha-Syuchatar 132 kV transmission line and upgrading the busbar capacity at the Syuchatar substation.

The eighth measure proposes installing a 132/66 kV transformer at Lamosangu. This is expected to improve electricity supply to Panchkhal, Melamchi and Banepa while increasing the effective transmission capacity available for Kathmandu.

Maximising Power Flow Through Existing Infrastructure

Alongside the construction of new transmission lines and substations, the NEA has also introduced a strategy to maximise the use of existing infrastructure.

The plan includes maximising power flows from all three sources—Matatirtha, Bhaktapur and Kulekhani—during winter, shifting loads as required and restructuring the transmission network.

The strategy also calls for N-1 contingency management and switching arrangements to prevent widespread power disruptions in the event of an outage involving a major transmission line or transformer.

Similarly, the document emphasises ensuring the availability of necessary equipment and spare parts, improving coordination among different transmission and distribution units, and keeping planned load shedding as a last resort.

Targeting 650 MW Peak Demand, Implementation Will Be the Real Test

Through its strategy, the NEA aims to reliably meet the Kathmandu Valley’s projected peak demand of around 650 MW during the coming winter. Thakur said the authority expects to improve the utilisation of existing infrastructure, reduce the risk of widespread power disruptions and ensure uninterrupted service to consumers.

However, having a total pooling capacity of 675 MW and being able to deliver the same amount of electricity to all parts of the Valley when needed are two different things. Actual supply depends on the availability of power sources, the effective carrying capacity of transmission lines, transformer loading at substations and the condition of the distribution network within the Valley.

Therefore, the success of the NEA’s winter roadmap will depend on its ability to complete the eight prioritised measures on time. In particular, addressing bottlenecks along the Matatirtha-Syuchatar-Balaju corridor, establishing alternative supply routes and managing heavily loaded substations are expected to make winter electricity supply in Kathmandu more reliable.

As electricity demand in Kathmandu continues to grow, simply arranging power from new generation sources will not be enough. Building and managing transmission and distribution infrastructure capable of delivering available electricity to areas where it is needed will be the key to preventing load shedding during the winter.

 