Sankhuwasabha, Nov 23: Prime Minister Balendra Shah and his Indian counterpart, Narendra Modi, are set to jointly lay the foundation stone for the Lower Arun Hydropower Project today on 23 November.
CEO of SJVN Lower Arun Power Development Company (SLPIDC), Pankaj Chaudhary shared that preparations for the foundation stone laying ceremony have reached the final stage.
He informed that Prime Minister Shah and his Indian counterpart Modi will unveil the project digitally from New Delhi today.
The project’s vital structures will be built in Chichila Rural Municipality and Khandbari Municipality of Sankhuwasabha.
Prime Minister Shah is currently in New Delhi on a two-day State visit.
SJVN Lower Arun Power Development Company shared that the digital foundation stone unveiling will be broadcast live at the project site. The project has a capacity of 669 megawatts.
Meanwhile, compensation amounting to Rs 999.83 million so far has been distributed to 253 local families affected by the project.
As many as 656 people living at the Lower Arun project construction site will receive compensation. The project will distribute a total of Rs 1.4 billion as compensation.
A total of 268 households will be directly affected by the project. The Indian company SJVN is constructing the Arun III Hydropower Project.
After electricity is generated from the under-construction 900 MW Arun III Hydropower Project, the water collected will be carried to the powerhouse in Khandbari Municipality–2, Chewabesi, through a tunnel of about 17.3 kilometers. The project’s estimated cost is Rs 92.67 billion.
According to the Project Development Agreement (PDA) between the Investment Board and the Indian company, the project will be built under a build, own, operate, and transfer (BOOT) model.
The government will get it free after 25 years of commercial electricity production in its current condition.
The construction period of the project will be five years. On 31 May 2023, the Investment Board Nepal and SJVN Lower Arun Power Development Company signed the Project Development Agreement (PDA).
Nepal will receive 21% of the total electricity produced by the project for free.
The construction of the project is expected to make a significant contribution to energy development, infrastructure expansion, and economic activities in Koshi Province, including Sankhuwasabha.